Tag Archive for: Everest

everest route Madison Sherpas open Everest Route!

Our Sherpas worked very hard today to break trail through waist deep snow and some strong winds. They have now established the climbing route to the summit of Mount Everest! They are now back at the south col high camp (camp 4).

The Rope Fixing Team Members are: Pasang Tenzing, Lakpa Dendi Sherpa, Pas Dawa Sherpa, Tenzing Gyalzen, Datuk Bhote, Pemba Sherpa, Jenjen Bhote, Siddhi Bahadur Tamang.

We are happy that our team made the first summit of Mount Everest in 2018. Now, hopefully many other climbers will be able to follow the route safely to the summit over the next week if we have good weather.

Ready To Move For Summit Push!

Today our madison everest team climbers with guides Garrett Madison, Conan Bliss, & Sid Pattison along with climbers Josh, Matt, Randy, Tym, & David are resting in base camp up . They are waiting to begin the summit rotation, this is the final rotation on Mount Everest and hopefully will culminate in reaching the summit! The weather has been windy, more so than the specialized weather forecasts have predicted. So, we have been conservative in our decision making and decided to hold here in base camp until the weather trend looks suitable for us to move us.

Then our Everest climbers will climb from Everest base camp through the Khumbu Icefall and negotiate the many ladders which span crevasses, sometimes about 20 ft. (6m) in width, along with the steep ice and vertical sections of the route. We will go up past Camp 1 through the Western CWM (Valley) to Camp 2, our Advanced Base Camp and from there take a rest day to re evaluate the weather, route conditions, etc.

Our 2 advance teams are already enroute on the final summit rotation! Ed & Ant, our first team, are at Camp 2, having moved up from Everest base camp 2 days ago, and are assessing the mountain conditions which includes the weather, the rope fixing progress, etc.

Our second advance team with Kenton, Ben, and Mark left Everest base camp yesterday and are currently also at Camp 2. They reported very good conditions in the Khumbu Icefall and after arriving at Camp 2 are also reassessing the mountain conditions in preparation for moving up higher on Everest.

Rope Fixing Update!

Our rope fixing Sherpas moved up to the South Col (Camp 4) yesterday in preparation to fix ropes from there to the Balcony (27,500 ft. / 8,333m), despite strong winds on the Lhotse Face. Yesterday we had a huge wind storm on Everest that lasted through the night and many teams lost tents at Camp 2, fortunately we had our entire Sherpa team (22 Sherpas plus camp staff) in our Camp 2 (Advanced Base Camp) so they were able to secure and protect our camp during this massive wind event. Thankfully, our Sherpas reached the South Col (Camp 4) and established a camp there, and then commenced the first part of the rope fixing project today, reaching the Balcony (27,500 ft. / 8333m).

Weather & Other Update!

If the weather is good, and mountain conditions are favorable (they reported deep snow on the route), and our team has the physical energy and mental fortitude, then hopefully our Sherpas will be able to finish the summit rope fixing and open the route by the end of May 12th, so that the route will be open for all climbers on Mount Everest by May 13th.

This is our plan, and with determination and good luck we expect our 4 teams of climbers (Sherpa rope fixing team, advance team of Ed & Ant, second team of Kenton / Ben/ Mark, and third team of Garrett / Conan / Sid with Josh / Matt / Tym / Randy / David to be reaching the summit of Mount Everest between May 12th and May 18th, weather pending! Fortunately the weather forecast looks good through May 21st, so we have a very good weather window in which to make our summit attempts. Thanks for your kind thoughts and prayers! We hope Mount Everest (‘Sagarmatha’ in Nepal) will grant us safe passage to the top of her peak and back!

electrical storm

Lightning, Thunder & Storm!

Last night at around 3 AM we had an exhilarating electrical storm here on Mount Everest complete with lightning, thunder, then a few inches of snowfall. Today our advanced climbing team (Ed & Ant) moved up from Everest base camp and will stay at Camp 2. The ‘Everest Link’ Internet WiFi system that most of the climbers here in Everest base camp rely upon was knocked out by a lightning bolt.  So, repairs are under way and hopefully the system will be back up and working again soon!
All of our climbing Sherpas are up in camp 2, and it was a good thing today because the winds have been very high at camp 2 . As a result many teams had tents damaged or completely blown away. Fortunately our Sherpas were able to secure and protect our tents in camp 2 from blowing away.
Our plan is to re-evaluate the weather tomorrow and see if rope fixing to the summit is reasonable over the next few days given the weather forecast. Hopefully, the winds will die down in the near future and make climbing possible.
Our main team of climbers is tentatively planning to move up from Everest base camp to camp 2 on May 11th . Then, will take a rest day at camp 2 and reassess the weather, route conditions, and feasibility of making a summit attempt. Everyone here in base camp is doing well and resting up for our final rotation. That is, our attempt at the summit of Mount Everest!

Ready For Summit Attempt!

Our team of Sherpas left Everest base camp early this morning and climbed to Camp 2, twenty two Sherpas in all. They will rest tomorrow and then 6 of our Sherpas along with 2 from Adventure Consultants team will head up to the South Col high camp (Camp 4), as long as the winds die down.  Then, begin the final stage of the rope fixing project to the summit of Mount Everest. Our plan is to have the route finished to the summit by May 12th, weather pending. Usually when the first climbers are setting the route to the summit they have to break trail through waist deep snow, and set the anchors and climbing rope along the route.

The first stage will be to move to the South Col and establish camp, the second stage will be to fix ropes up the Triangular Face to the Balcony (27,500 ft. / 8333m), and the third stage will be to fix ropes from the Balcony up the South East ridge to the rock bands just below the South Summit of Mount Everest, over the South Summit, and then along the summit ridge to the top of Mount Everest! We hope the weather and route conditions will be favorable for our Sherpas as they work hard to establish the final section of the climbing route to the top of the mountain for our team and all teams on Mount Everest, so that all climbers may have the opportunity to climb safely and efficiently.

Team Updates!

Our climbers are all now in Everest base camp and some who took a 4 day rest in Namche are back now so we are all together as we make final preparations for our summit attempt! We are checking our equipment and readying our minds and bodies for this epic challenge, the culmination of our last 6 weeks here in Nepal. In the next couple of days we will be moving up to Camp 2 (our Advanced Base Camp) and from their we will reassess the summit rope fixing progress, the weather forecast, the mountain conditions, and make a final decision on moving up to the higher camps on schedule for our summit attempt!

Second Rotation Succeed!

We concluded a great second rotation today by descending from our Camp 2, known as our Advanced Base Camp, all the way down to our Everest base camp. While on our rotation we spent three nights at our Camp 2, and were very lucky to have great weather. To begin our rotation, we departed our base camp at 4 AM and climbed all the way to Camp 2.

Then, we took a rest day to recuperate and recover from the big climb, nearly 4,000 ft (1,212m) of vertical gain. After our rest day we planned to climb to our Camp 3 on the Lhotse Face, so we departed our Camp 2 (Advanced Base Camp) at 8 AM .We climbed with our down suits to the base of the Lhotse Face, then began our ascent up the steep ice wall on the fixed ropes towards Camp 3. It is situated about halfway up the Lhotse Face at approximately 23,500 ft. (7,121m).

The Lhotse Face is notably icier this year and requires good crampon technique! After 5 hours of climbing we reached our Camp 3 and took a long break to rest, hydrate, and eat a few snacks. We also had the privilege of enjoying an amazing view from Camp 3, looking down over Camp 2, the Western CWM, and Camp 1. We then descended the fixed rope designated for rappelling and made good time in our descent, reaching our Camp 2 just an hour later for a late afternoon lunch. It was a very productive rotation in that we accomplished our goal of climbing to Camp 3 to acclimatize . Additionally, we also familiarize ourselves with the steep and technical terrain of the Lhotse Face.

Rope Fixing Update!

Our Sherpas have been busy carrying loads of equipment to the South Col high camp (Camp 4) for the final stage of the rope fixing project . This involves setting the ropes from the South Col to the Summit of Mount Everest. They have done an exemplary job so far by setting two lines up to Camp 3. One for ascending and one for descending, as well as an additional line above Camp 3 to ease congestion on the route. We have received many compliments regarding how the lines are set in a safe and desirable fashion on the Lhotse Face which makes for efficient climbing.

Lines have also been set on the Geneva Spur, the final rock ridge before the South Col, so that climbers can go up and down on separate lines for safety and efficiency. At this time Sherpas have been utilizing these ropes to carry loads of oxygen cylinders, tents, food, and fuel to position at the South Col for the eventual summit attempt on Mount Everest!

Weather Forecast!

According to our weather forecasts, it appears that a major wind event is approaching Mount Everest, probably in the next day or two. Our Sherpas will make good use of tomorrows marginal weather forecast to position additional loads at the South Col high camp, and then see if the following day is appropriate for climbing above 8000 meters. The jet stream will likely cover the Mount Everest region for up to a week and no climbing will take place above 8000 meters during this time, so we are preparing to hold tight and wait for the opportunity when the Jet Stream passes and the winds are calm enough for a summit attempt! Until then we plan to rest and enjoy the amenities of our Everest base camp!

Mission Everest Continues!

Yesterday the weather was good up here , we took some rest in Camp 2. Today we departed Camp 2, our Advanced Base Camp, at 7 AM to climb up the Lhotse Face to Camp 3 at nearly 23,500 ft. (7120m) We donned our Down Suits to stay warm in the early morning before the sun arrived on the Lhotse Face at around 9 AM. Climbing up the steep ice was challenging, but our steel crampons held firm as we made our way up the face to Camp 3.

Upon reaching Camp 3 we took a long break and had a snack before making our way down the Lhotse Face, rappelling the steeper line over the blue ice to the base of the Lhotse Face near the Bergschrund. We then made our way back to Camp 2 for dinner and a restful sleep. Our plan is to either descend tomorrow or take a rest day and descend the following day down to Everest base camp, and then take a long rest before embarking on our summit rotation!

Today our climbing sherpas carried loads to the South Col high camp (Camp 4) in preparation for the final rope fixing to the summit of Mount Everest – Our Rope fixing team fixed the rope upto South Col! . Now that all of the essential equipment is in place for the rope fixing (ropes, ice screws, carabiners, oxygen, etc) we are keeping an eye on the weather for an opportunity to fix the final portion of the route up the Triangular Face to the Balcony (27,500 ft / 8335m), then up the south east ridge and over the rock bands to the south summit, along the summit ridge to the top of the world! Stay tuned for updates from our rope fixing team!

Today we departed Mount Everest base camp at 4 AM and climbed up through the Khumbu Icefall in the pre dawn hours when the ice is solid. Then we had the pleasure of a beautiful sunrise as we ascended up through the Icefall to Camp 1. After reaching Camp 1 we continued up through the Western CWM (valley) to Camp 2, our Advanced Base Camp. It was a long day of climbing, but we are happy to finally have arrived in our Advanced Base Camp on Mount Everest and now looking forward to a rest day tomorrow! Everyone is doing well here on Mount Everest!

Today our Sherpas carried 10 loads of ropes and hardware from Camp 2, our Advanced Base Camp, to the South Col high camp (Camp 4) on Mount Everest.  This load carry is approximately 4,500 ft. (1380m) from Camp 2 to Camp 4, and very strenuous day, which involves climbing the steep ice of the Lhotse Face, crossing the rock formation known as the Yellow Band, and then up and over the secondary rock formation known as the Geneva Spur, a ridge line which separates the upper Lhotse Face.  Our Sherpas are planning to carry another 10 loads of essential equipment tomorrow, to complete the positioning of gear necessary for the rope fixing project to reach the summit of Mount Everest.

Mountain Hardwear Backpacks to Summit!

For our 2018 expedition we are using these backpack from Mountain Hardwear. Also, our Mountain Hardwear ‘South Col’ backpacks are utilized by our climbing Sherpa to transport the essential equipment in harsh environment . Furthermore, these backpacks  are used for rope fixing all the way to the summit.


Second Rotation And Rope Fixing Updates !

Our team of climbers is heading up tonight on our second rotation on Mount Everest to acclimatize. Additionally, they will carry essential equipment to our high camps such as our down suits, mittens, hand warmers, and electric foot warmers in preparation for our summit rotation in a couple weeks time. We have been resting up here in Everest base camp the last few days . We are ready to make our second trip up Everest to climb the Lhotse Face to Camp 3. Our plan is to touch Camp 3 and then return to Camp 2 for the night. We should be back in base camp in 4 or 5 days time.

The goal of this second rotation is to continue building our acclimatization and increase our familiarity with the route . Furthermore, to become more efficient in our climbing through the Khumbu Icefall, Western CWM, and the Lhotse Face which is more icy this year than in previous seasons.

Our rope fixing sherpas are currently in Camp 2 on Mount Everest and will be carrying loads of rope and hardware (ice screws, carabiners, oxygen, etc.) to the South Col high camp (Camp 4) tomorrow and the following day. And, hopefully depositing all essential equipment for the rope fixing project at the South Col. After this load carry they will take a rest and we will evaluate the weather forecast for the final stage of the rope fixing project. Evaluation involves setting the ropes from the South Col high camp (Camp 4) to the summit, a multi day project. We hope for good weather and route conditions for this project to continue moving forward in a timely manner.


We are planning our second rotation up Mount Everest . Also, focusing on moving the ropes and equipment up to the South Col for the rope fixing to the summit.